UltraBond Floor System speeds up Apartment Building Construction

A composite floor system shortened construction time by three months and cut material costs, for an 11-storey, 166-condo unit apartment building in Longueuil Quebec. The system, called UltraBond, comes in cold-form sheets 609.6mm (24 inches) wide, 203mm (8”) high and precut in lengths up to 10.06m (33 ft.), according to Simon Pawsey, technical sales representative with the Steelform Group of Companies.

Jump to specs

Once assembled into floor decking and with rebar placed in the deep V-grooves, concrete is poured on the Ultra-Bond, creating a lightweight composite floor 292mm (11.5”) thick. Once finished, it has a two-hour fire rating. Pawsey checks off some of the advantages of this construction technique:

“UltraBond significantly reduced weight on the structure
compared to a conventional slab. It reduced shoring to one
row. Cost savings were a big factor, with one-third of the rebar
and 50 percent less concrete than a nine-inch slab. It saved the
general contractor about three months of construction time.”

The UltraBond used in the structure, including the balconies,
was 1.22mm (.048”) Z275 (G90) galvanized steel. The contractor
used 13,066m2 (140,000 sq. ft.) of UltraBond deck, weighing
about 226,796 Kg (500,000 pounds). Because of the lighter
weight, less shoring is required.

Close up of Balconies under construction
Apartment Building Under Construction

Axcès Saint-Charles in Longueuil, Québec, built with the UltraBond composite floor system and light steel framing. Rebar creates reinforced beams in the UltraBond composite floors, using 22mm (.048”) Z275 (G90) galvanized steel.

Contractors and steel beams of building under construction

UltraBond steel deck, rebar, mesh and concrete form a composite floor that is lighter than conventional concrete floor construction.


All images courtesy: Steelform Group

LIGHT STEEL FRAMING:

G60 galvanized 1.22mm to 2.74mm (.048” to .108” )

Actual dimensions of the LSF supplied 152.4mm (6") studs

UltraBond – Z275 (G90) galvanized 1.22mm (.048”)

DESIGN AND CONSTRUCTION TEAM
CLIENT:

Habitations Trigone 450-446-8221

STEEL BUILDING SYSTEM SUPPLIER:

Steelform Group of Companies 514-210-0903

ARCHITECT AND PROJECT MANAGER:

Atelier Urban Face 514-931-9168

STRUCTURAL ENGINEER:

CPF Groupe Conseils 514-667-5450

STEEL STUD SUPPLIER:

Produits de Bâtiment Fusion 450-728-4500

STEEL ERECTION:

Les Installations Miral 450-492-5952

BUILDER:

Habitations Trigone 450-446-8221

PHOTOGRAPHY:

Simon Pawsey 514-210-0903

Most Popular

View All

Inside Steligence®…

It was a Tuesday morning at the Canadian Steel Conference, and most of the …

Steel Receipts…

The day I spoke to Stan Lipkowski, Principal Projects Manager – Sustainab…

Prefabricated Light …

Interbuild’s pre-fabricated steel wall panels, together with a faster con…

Home Steel Home…

Steel is the go-to material for industrial and commercial construction. But…

Community boasts net…

Grow Community is a development that appeals to individuals and families lo…

Go Figure…

For cities and communities across the globe, the centre of public life isn&…

Big build on the pra…

At the southern edge of Alberta, the prairie fields stretch as far as the e…

Great Big See…

At the turn of the 19th century, Donald ‘Og’ MacNeil and three …

It’s What’s on t…

Tim Verhey has a problem with Steel Design Magazine. “You write too much …

Weathering reflectio…

Go for a walk around Sudbury, and you’ll find traces of both the region&#…

Building better with…

On the shore of a northern Canadian lake, the need to respect the natural w…

Solving the Canadian…

Cities are economic engines. They have the greatest concentrations of compa…